Short answer: Texas commercial due diligence is the structured review of a property, project, budget, and legal path before an owner or investor commits capital. The safest approach is to verify site control, entitlements, condition, utilities, budget, financing, schedule, and operating assumptions in writing—then turn unresolved risks into priced decisions.

What does Texas commercial due diligence include?
Due diligence is not one inspection. It is a coordinated review that answers whether the deal can be built, funded, opened, and operated as planned. Requirements vary by site and jurisdiction, so verify the local development rules, utility service, lender conditions, and project assumptions for the property at hand.
Our multifamily feasibility study tests the site, budget and schedule before you buy the land; for leased space, commercial buildout advisory covers pre-lease feasibility before you sign.
| Risk area | Evidence to verify | Decision to document |
|---|---|---|
| Site and title | Survey, title commitment, easements, access | Can the planned use fit the site? |
| Entitlements | Applicable land-use and development rules, plat, permits, deed restrictions | What approvals and timing are required? |
| Physical condition | Property condition assessment, roof, structure, MEP | What repairs or replacement reserves are needed? |
| Budget and financing | Estimate, allowances, contingency, lender conditions | Is the all-in cost financeable? |
| Schedule and operations | Milestones, long-lead items, staffing and opening plan | When can revenue realistically begin? |
12-point commercial due diligence checklist
- Confirm site control. Review the contract, title commitment, survey, legal description, access, parking rights, and recorded easements.
- Test the intended use. Confirm applicable land-use and development rules, platting, deed restrictions, permits, certificates, and inspections with the relevant jurisdiction. Houston has no zoning ordinance, but its development regulations and recorded restrictions still matter.
- Check flood and drainage exposure. Compare the site with FEMA flood maps and obtain a civil engineer’s view of detention, grading, and stormwater obligations.
- Verify utilities. Get written confirmation of water, sanitary sewer, power, gas, telecom capacity, tap fees, and connection lead times.
- Order a condition review. Inspect structure, envelope, roof, HVAC, electrical, plumbing, fire protection, accessibility, and hazardous materials.
- Validate the program. Convert the business plan into a room list, area schedule, equipment list, parking count, and performance requirements.
- Build an all-in budget. Include land, design, surveys, geotechnical work, permits, utility fees, construction, furniture and equipment, financing, insurance, taxes, and contingency.
- Stress-test the budget. Model escalation, interest-rate changes, delayed opening, a scope increase, and at least one downside case before closing.
- Review the delivery plan. Compare design-bid-build, negotiated GMP, design-build, and phased delivery against the owner’s risk tolerance.
- Map the schedule. Identify approvals, procurement packages, long-lead equipment, utility work, inspections, commissioning, and the opening date’s true critical path.
- Document responsibilities. Assign who owns each risk, decision, submittal, allowance, and change; unresolved items should have an owner and due date.
- Issue a go/no-go memo. Summarize verified facts, open risks, cost ranges, schedule ranges, assumptions, and the conditions required to proceed.
How to use a red-yellow-green risk review
Use green for verified facts with an acceptable impact, yellow for an item that needs pricing, clarification, or a contingency, and red for a condition that could stop the project or materially change the deal. A yellow item is not a reason to ignore the risk; it is a prompt to assign a dollar amount, responsible party, and deadline.
For a practical owner-side process, pair this checklist with Epex Consulting’s owner’s representation services and request a project review before signing a purchase, lease, or construction contract.
Frequently asked questions
How long does commercial due diligence take in Texas?
Timing depends on the transaction, site, documents, and scope of specialist reviews. Set the review period around contractual deadlines and allow time to verify title, survey, environmental, utility, and permitting information before committing.
Who pays for due diligence?
The buyer, owner, or developer typically pays, although lenders and sellers may provide documents or studies. The cost is small compared with the cost of discovering a site, scope, or budget problem after closing.
Is a property inspection enough?
No. A physical inspection does not confirm applicable development rules, title, utility capacity, financing conditions, constructability, or the schedule to open. Those workstreams must be reviewed together.
Should a lender be involved early?
Yes. Early lender feedback can reveal appraisal, insurance, draw, reserve, reporting, or completion requirements that change the budget and delivery plan.
What is the biggest Texas due diligence mistake?
A costly mistake is treating an estimate or broker statement as a verified fact. Require source documents, record assumptions, and price the unknowns before you commit.
Next step
Epex Consulting helps commercial owners, investors, franchisees, and developers coordinate owner-side risk reviews across Texas, including Houston, Dallas–Fort Worth, Austin, San Antonio, and other markets. Book a project review to turn your open issues into a clear decision plan.
Disclaimer: This article is general information, not legal, tax, engineering, architectural, environmental, or financial advice. Engage qualified Texas professionals for project-specific decisions.