AIA G702 and G703 work together in a construction pay application, but they do different jobs. The G702 is the summary and certification page. The G703 is the line-item continuation sheet that shows where the money has been billed.

This practical comparison explains AIA G702 vs G703, how the figures connect, and what owners, developers, and lenders should verify before approving a draw.

Free download: Schedule of Values & Pay Application Worksheet (Excel)

A G703-style line-item sheet that rolls up into a one-page application summary and flags the mistakes that cause overpayment: a contract sum that doesn’t match the schedule of values, mismatched retainage, lines billed over 100%, and pending change orders slipped into the total. It opens with a worked example you can overwrite.

Download the worksheet (.xlsx)

Not an AIA document. If your contract or lender requires the official forms, use this to prepare and check the numbers.

FREE OWNER RESOURCE KIT

Get the free pay-application worksheet

Enter your name and email to access the Excel worksheet, along with our Texas lien waiver forms and tracker. The files appear after you submit. No payment required.

We use your details to respond to your resource request. Privacy Policy

Need help with a live draw? Explore construction draw administration services, use the draw inspection checklist, or see the eight-unit Houston townhome draw-administration case study. The worksheet is a preparation aid, not an official AIA form or approval to release funds.

AIA G702 vs G703: the difference at a glance

FormPrimary purposeWhat it shows
G702Application and certificate for paymentContract-level summary: original contract, approved changes, completed and stored work, retainage, prior payments, current payment due, and balance to finish
G703Continuation sheetLine-item detail by trade or schedule-of-values category: scheduled value, prior work, current work, stored materials, total completed, percent complete, and balance

Put simply: the G703 builds the detail; the G702 reports the result. If the G703 does not reconcile to the G702, the pay application is not ready for approval.

AIA G702 vs G703: the payment application summary and the continuation sheet reviewed together on a Texas draw

What is the AIA G702?

The G702 is the top-level payment application. It summarizes the contract and calculates the amount currently due after accounting for approved change orders, completed work, stored materials, retainage, and previous payments.

Owners and lenders use the G702 to answer questions such as:

The form also includes the contractor’s certification and the architect’s certification where the project agreement requires architect review.

What is the AIA G703?

The G703 is the continuation sheet supporting the G702. It breaks the contract into schedule-of-values lines so reviewers can see how much has been billed against each scope category.

A useful G703 is specific enough to evaluate progress. A schedule containing only “general requirements,” “construction,” and “closeout” may add up mathematically but is too broad to verify in the field. Trade-level or work-package detail makes percent complete defensible.

Where to get the official AIA G702 and G703 forms

AIA publishes free, non-executable samples of both forms, which are useful for seeing the layout before you buy:

To use the forms on a project, license them through AIA Contract Documents. Many lenders accept the contractor’s own pay-application format as long as it carries the same information. Check the loan agreement before assuming the official forms are required.

The standard G702 includes a notary block under the contractor’s certification. Whether notarization is actually required depends on your contract and lender. Don’t confuse this with Texas lien waivers, which no longer need to be notarized for original contracts entered into on or after January 1, 2022.

AIA G702 vs G703: how the two forms should reconcile

  1. Contract sum: the original contract plus approved changes on the G702 should equal the current total scheduled value represented in the G703.
  2. Completed and stored to date: the total of the completed-work and stored-material columns on the G703 should flow to the corresponding G702 total.
  3. Retainage: retainage calculated from the G703 detail should match the G702 summary, including any different retainage rates.
  4. Current payment due: completed and stored work less retainage and prior certificates should equal the current amount requested.
  5. Balance to finish: the remaining G703 line-item balances should support the balance reported on the G702.
Houston townhome development funded on AIA G702 vs G703 pay applications reviewed by the owner’s rep

Worked example: how G703 lines become the G702 numbers

An illustrative restaurant build-out, pay application #3. The original contract is $480,000. Change order #1 (a larger grease interceptor, +$12,500) is approved. Change order #2 (bar millwork, $8,000) is still pending. Retainage is 10% on completed work and on stored materials. The rooftop unit has been delivered and stored on site but not installed.

The G703 side (line items)

G703 illustrative line-item example
#ScopeScheduled valueFrom previousThis periodStored nowCompleted & stored%Balance
1General conditions$38,000$11,400$3,800—$15,20040%$22,800
2Demolition$14,500$14,500——$14,500100%$0
3Framing & drywall$62,000$31,000$18,600—$49,60080%$12,400
4Plumbing (incl. CO #1)$58,500$23,000$9,200—$32,20055%$26,300
5HVAC & kitchen exhaust$86,000$17,200$12,900$21,500$51,60060%$34,400
6Electrical$71,000$21,300$14,200—$35,50050%$35,500
7Finishes$68,500———$00%$68,500
8Storefront & doors$42,000———$00%$42,000
9Fire sprinkler & alarm$32,000$6,400$6,400—$12,80040%$19,200
10Closeout$20,000———$00%$20,000
Totals$492,500$124,800$65,100$21,500$211,40042.9%$281,100

The G702 side (summary)

G702 illustrative payment summary
LineItemAmount
1Original contract sum$480,000.00
2Net change by approved change orders$12,500.00
3Contract sum to date$492,500.00
4Total completed & stored to date$211,400.00
5Retainage (10% of $189,900 completed + 10% of $21,500 stored)$21,140.00
6Total earned less retainage$190,260.00
7Less previous certificates for payment$112,320.00
8Current payment due$77,940.00
9Balance to finish, including retainage$302,240.00

Three things to notice:

The free worksheet opens with this example, so you can see every formula and then replace the numbers with your own.

Common AIA G702 vs G703 errors

Unapproved changes included in the contract sum

Only approved changes should change the contract sum. Pending change orders belong in a separate log until the approval required by the contract is complete.

Stored materials counted twice

When materials are installed, their value should move from stored materials into completed work. Leaving the amount in both locations overstates progress. In the example above, if the rooftop unit were installed next month and its $21,500 billed as completed work while also staying in “stored now”, the application would overstate progress by $21,500, and the owner would pay $19,350 too much after retainage.

Prior payments do not match the last certificate

The prior-certificate figure should carry forward from the previously approved payment. A mismatch may create a duplicate payment or an unexplained shortfall.

Retainage is calculated inconsistently

This is the most common AIA G702 vs G703 mismatch we see on Texas draws: the G702 summary carries one retainage percentage while the G703 lines carry another.

Projects may apply one rate to completed work, another to stored materials, or reduce retainage for selected trades. Whatever the contract requires must be applied consistently and documented. In the example, holding 5% on the line items while the summary says 10% creates a $10,570 gap between the two forms.

Percent complete is based on invoices instead of progress

Supplier and subcontractor invoices are supporting documents, not automatic proof that the owner received the value billed. Field verification and a remaining-cost review still matter.

Documents that should accompany the AIA G702 vs G703 pay application

Owner and lender AIA G702 vs G703 review checklist on a commercial build-out

Owner and lender AIA G702 vs G703 review checklist

  1. Do the G702 and G703 reconcile exactly?
  2. Does the current contract sum include only approved changes?
  3. Does field progress support the amount billed by line item?
  4. Are front-loaded lines, stored materials, and general conditions defensible?
  5. Are required waivers complete through the appropriate payment period?
  6. Does the remaining balance appear sufficient to complete each scope?
  7. Are schedule delays or quality deficiencies reflected in the recommendation?

Who prepares and who reviews the forms?

The forms themselves are published by the American Institute of Architects; the current editions are the G702-1992 Application and Certificate for Payment and the G703-1992 Continuation Sheet. In Texas the lien waivers that travel with them follow the statutory forms in Property Code Chapter 53.

The contractor commonly prepares the payment application from its approved schedule of values. The architect may review and certify payment under the project agreements. The owner, lender, owner’s representative, or draw administrator may perform additional document and progress review before funds are released.

The contracts control the formal approval path. A clean process assigns responsibility for preparation, certification, lender inspection, owner approval, and final funding before the first draw.

In Texas, retainage has a statutory side too. Property Code §53.101 requires the owner to reserve 10% of the contract price, or of the value of the work, during the job and for 30 days after completion. The retainage line on the G702 is a contract term. Setting it at 10% keeps the two aligned, but your contract governs. Lien waivers travel with each draw as separate documents; see our Texas lien waiver forms guide. This is general information, not legal advice.

Frequently asked questions about AIA G702 vs G703

AIA G702 vs G703: can a project use a G702 without a G703?

A very small contract might be summarized without a multi-line continuation sheet, but most projects need the line-item detail to support the summary. Lender and contract requirements govern.

Is a schedule of values the same as the G703?

Not quite — and the AIA G702 vs G703 distinction is easiest to see here: the schedule of values is the agreed breakdown; the G703 is that breakdown with this period’s progress filled in.

The approved schedule of values provides the line-item structure. The G703 applies current-period, prior-period, stored-material, retainage, and balance information to that structure for each pay application.

Does AIA G702 vs G703 paperwork replace lien waivers?

No. The payment application reports amounts requested and certified. Lien waivers address payment rights and should be tracked as separate required documents.

Can Epex take over a draw process mid-project?

Yes. The first step is a funded-to-date reconciliation against the current contract sum and schedule of values, followed by a review of change orders, waivers, stored materials, and prior payment records.

What does G702 mean?

G702 is the AIA document number for the Application and Certificate for Payment, the one-page summary a contractor submits to request a progress payment. The current edition is G702-1992. Its companion, G703, is the Continuation Sheet with the line-item detail.

Is there a free G703 template?

AIA sells the official form and offers a free sample to view. Our free Schedule of Values & Pay Application Worksheet follows the same line-item logic (scheduled value, previous, this period, stored, completed to date, balance, retainage) and checks the math. It isn’t an AIA document, so use it to prepare or check numbers when the official form isn’t required, or alongside it when it is.

How is retainage shown on the G702?

Line 5 of the G702 shows retainage on completed work and on stored materials separately, because some contracts use different rates for each. The total has to match the retainage calculated line by line on the G703.

Can stored materials be billed on the G703?

Usually, if the contract and lender allow it. Most lenders want stored materials itemized, backed by invoices, insured, and stored on site or in a bonded warehouse. Once installed, the value moves from “stored” to “completed”.

Epex Consulting AIA G702 vs G703 draw administration, Houston Texas

Make the next AIA G702 vs G703 draw lender-ready

Epex Consulting provides construction draw administration for multifamily and commercial projects, including schedule-of-values reconciliation, lien-waiver tracking, lender coordination, and audit-ready files. Use our construction draw inspection checklist or review the 8-Unit Townhomes case study.

Book a free 20-minute project review and bring the current G702, G703, change-order log, and last approved draw.